Application for Plan Certification and Building Inspection for Small-Scale Development Proposals

All applications for building plan and mechanical & electrical plan certificates must be submitted through the Local Authority (LA) One Stop Centre (OSC) where the project is being constructed. Consultants may refer to Processing Category Table to submit an application to the relevant OSC.

Consultants must submit a formal application letter and comply with the Technical Plan Submission Requirements Checklist (technical plan). building and plan M&E) when submitting the plans. Subsequently, both plans will be distributed by the OSC to the Malaysian Fire and Rescue Department (JBPM) in accordance with Processing Category Table.

JBPM will provide a comment within 7 days from the date of receipt to the PBT and subsequently issue a clearance letter.

BUILDING INSPECTION APPLICATION FOR THE ISSUANCE OF A JBPM RELEASE LETTER CERTIFICATE OF COMPLETION AND COMPLIANCE (CCC)

Building inspection applications for the issuance of a JBPM Clearance Letter must be submitted through the Local Authority (PBT) One-Stop Centre (OSC) where the project is being built. The inspection application must comply with and attach Fire Safety Inspection Application Checklist Form together with the required documents.

The inspection fee must be included when submitting the inspection application. Payment can be made via money order or bank draft or cheque must be made out to the Director General of the Malaysian Fire and Rescue Department.

The inspection application will be forwarded by OSC to JBPM according to Processing Category Table to determine the inspection date. The inspection will be carried out within seven days after the clearance letter from Tenaga Nasional Berhad (TNB) and the Water Authority is issued. The JBPM Clearance Letter will be issued to the applicant on the same day the inspection is carried out. 

Note: Inspections for residential buildings not exceeding 18 metres in height are exempted.